Separate size from plan
5 min · Turn disagreement into evidence
A size is a view of work under assumptions. A forecast adds evidence about capacity, past performance and the decision horizon. Do not force deadline pressure into a size.
Reading
coreLabel the object
Before debating a number, label each statement as size, uncertainty, capacity or decision constraint. The Scrum Guide says Developers are responsible for sizing and that Sprint forecasts consider past performance, upcoming capacity and the Definition of Done. It does not prescribe story points.
Worked example and transfer practice
All examples below are fictional teaching material. Use synthetic notes; no workplace or personal data is required or uploaded.
The number and the plan answer different questions. A fictional export item includes audit logging and migration of existing records. Those are work-boundary questions. An unfamiliar supplier creates uncertainty about that work. Two Developers being unavailable next week is a capacity fact for forecasting; it does not remove the migration from the item. Relative size is not a unit of calendar time, and one team’s scale is not portable to another.
Try before reading the guide: Classify each statement: the export now needs an approval record; one engineer is on leave; the supplier may rate-limit requests; the release must precede an audit. Explain where each belongs in the next discussion.
Practice review guide
These concern scope, capacity, uncertainty and a decision constraint respectively. Dependencies can affect both the work and elapsed delivery time, so identify the mechanism rather than forcing every fact into one exclusive category.
References
Knowledge check
corePractice · formative check
Separate size from forecast
Identify the statement that belongs in forecasting rather than sizing.
Concepts: sizing, forecasting
There is no attempt limit or pass/fail state. Completing the check only enables the lesson's separate explicit completion control; it never records completion or certificate eligibility itself.
Activity ready. Attempts are unlimited. Completing this practice activity enables the lesson's separate, explicit completion control.
Equivalent non-interactive path
Answer and feedback guide
Which statement should be handled in the delivery forecast?
- Two team members will be unavailable next week (best answer): Correct. Availability changes capacity, not the inherent size of the item.
- The item includes an unexamined data migration: That changes the understood work and should be exposed during sizing.
- People disagree about whether audit logging is included: Resolve the scope boundary before accepting a size.